BOARD RECAP
The Board of Education met in regular session on Monday, May 15, 2006 in the boardroom of the Fayette County Board of Education. The following actions were taken:
1. Approved agenda
2. Invocation – A moment of silence was observed
3.
Pledge of Allegiance – Meghan and Michael Plunkett – 5th
grade,
4. Student and Employee Recognitions
5. Resolution for Retirees
6. Comptroller Lee Davis reported that the monthly finances are in order
7. Approved personnel as presented including the reclassification of Randy Hudson, assistant principal at Fayetteville Intermediate, to principal of Spring Hill Elementary. He replaces Michael Howell who is retiring.
8. There were no comments from the public
9. Approved consent agenda
10. Items requiring action by the Board
a. Approved Easement for golf cart path and sewer at Panther Path
b. Approved Policy IFAB – Instructional Media and Equipment Revision
c. Approved Policy JBC – School Admissions
d. Approved new job descriptions – Exceptional Children’s Elementary Transition Program Teacher – Program housed at Spring Hill Elementary
e. Approved Social Studies textbook adoption
f. Approved
g. Approved tentative adoption of the FY 2007 – on table for 30 days
11. Superintendent’s Report
a. Wellness Program Policy presentation
b. Smaller Learning Community Grant presentation
c. GPS Update for Math
d. GPS Update for Science
e. Career Technology Local Plan for FY 2006 – 2007 - on table for 30 days
f. Update on Construction Program
The concrete footings for the entire building have been
poured. The concrete slabs for the kitchen, cafeteria, administration, media,
gym, art, music, technology and one fourth of the classroom areas have been
poured. The structural steel has been
erected in the kitchen, cafeteria, media, administration, art, music and
technology areas. The concrete masonry unit walls are being constructed in the
kitchen, cafeteria and administration areas.
The brick exterior wall on the 700 and 800 classroom addition
is approximately 95% complete.The exterior brick wall has begun on the 600
classroom addition. The lockers have
been installed in all three classroom additions. The window frames have been
installed in the three classroom additions. The glazing has been installed in
the 700 and 800 classroom additions. The fire protection has been installed in
all three classroom additions. The ceiling grid has been installed in all three
classroom additions.
The contractor is preparing shop drawing submittals.
The owner/contractor contracts have been received and are being reviewed for signatures. The contractor is preparing shop drawing submittals.
The contractor is preparing shop drawing submittals.
The contractor is preparing shop drawing submittals.
Brooks Elementary School
The architects have developed some preliminary design drawings for the addition. We have met with Brook’s zoning administrator.
The architects have developed a preliminary design for the kitchen modification. The preliminary design has been submitted to Mrs.Calhoun for her review.
12. There were no other matters to come before the board
13. Adjourned to executive session for discussion of real estate, personnel and Student Disciplinary Tribunal Appeal
14. Returned from executive session
15. Action relating to executive session – voted to uphold tribunal decision
16. Adjourned