BOARD RECAP
The Fayette County Board of Education met in regular session on Monday, May 21, 2007 in the boardroom of the Fayette County Board of Education. The following actions were taken:
1. Approved agenda
2.
Invocation – Pastor Eddie Thomas,
3. Pledge of Allegiance – Shannon Hinds, Aaron Sunil, Claire Bertram, 5th grade students, Peachtree City Elementary
4. Resolutions for retirees
5. Recognitions
a. Student Recognitions
Science Fair Awards
State Geography Bee
Governor’s Honor Program 2007 recipients
Rising
b. Employee Recognition
Georgia Master Teacher
c.
d.
6. Monthly Financial Report – Comptroller Lee Davis presented March and April financial reports.
7. Approved personnel as presented including the reclassification/election of the following:
Angie Southers, teacher at Oak
Grove Elementary to assistant principal of
Melvin Blocker, assistant
principal
8. There were no comments from the public
9. Approved consent agenda
10. Items requiring action by the board
a. Approved change meeting date from July 23, 2007 to July 31, 2007
b. Approved graduation coach proposal
c. Approved Oak Grove Elementary kitchen equipment bids – Manning Brothers
d. Approved bids for flooring and painting
e. Approved tentative approval of 2008 budget
11. Superintendent’s Reports
a. Update on classification/compensation
b. Residency change
c. Update on construction program
The generator is being installed. The
fire alarm annunciator panel is being installed. The punch list items are being addressed by
the contractor. The substantial completion and the certificate of occupancy
milestones are very near.
All
the kitchen equipment is on site and is being connected. The ceiling tile has been installed. The
substantial completion and certificate of occupancy for the kitchen are just a
few weeks away from being achieved.
All
the replacement roof-top HVAC units and the four new gymnasium HVAC units are
on site.
Brooks Elementary School
The ceiling grid, border ceiling tile and the light fixtures have been installed in all the classrooms. The walls have been painted. The door frames have been painted. The windows have been installed.
The brick is on order. The replacement HVAC rooftop units
are on order for installation this summer.
New Elementary School # 1
The building pad and the northern detention pond have been graded. The parking lot is being graded.