Minutes
Construction
Advisory Committee Meeting
April
10, 2006
Committee Members
met in the Fayette County Board of Education Central Office #2 Conference
Room. The Committee Members reintroduced
themselves. Dr. John DeCotis,
Superintendent, and Mr. Fred Phillips, Purchasing Agent, thanked everyone for
coming to the meeting.
Mr. Klaus Darnall, Construction Manager, and
Mr. Phillips reported on most recent FY2001 Bond updates at McIntosh High School. The old automotive program space is being
reconfigured to house the construction class, and the old construction
classroom will house the new health occupations program. The work on this project has begun, and will
finish around June 1, 2006. The
acoustical panels for the band room will be installed during spring break or
the summer.
Mr. Darnall and Mr. Phillips
reported on the FY2005 bond construction projects. Construction of the new middle school,
Bennett’s Mill Middle School, has begun. The concrete slabs have been poured for the
gymnasium, kitchen and cafeteria. Steel
for the structures of the kitchen and mechanical room is on site and awaiting
installment. The asphalt track around
the football field has been placed.
Sewer lines and electrical conduit is being installed for the classroom
areas, and the concrete slab will be poured for the media center in the near future. Weather permitting, the school is scheduled
to be opened on August 1, 2007.
On the Rising Starr
Middle School addition,
the concrete walls are 99% complete in the three wings, and the brick work is
being installed. The window framing
process has begun on the 800 wing. More
bricks were ordered in September to complete the building and match with the
brick originally placed on the school, and small shipments of these bricks are
coming in. The color of the new bricks
is not an exact match to the old bricks, and hopefully the brick work will be
completed in the next few weeks. The estimated completion date for this project
is August 1, 2006.
The Peeples
Elementary School and
Spring Hill Elementary additions are progressing. For Peeples Elementary School,
the contractor has poured the concrete building slab, and the hollow metal
doorframes are being set in the corridor.
The project is behind schedule due to a contractor mistake, and the
contractor assures Mr. Darnall that the lost time
will be made up in order to complete the addition by the scheduled August 1,
2006 date. The Spring Hill addition has
made good progress. The steel structures
for the addition have begun; the mezzanine slab is ready to be poured, and
exterior block wall is 52% complete. For
this project, the brick was ordered to match the existing brick, and the
shipments are coming in small amounts.
The estimated completion date for the project’s completion is August 1,
2006.
For Flat Rock Middle and Whitewater Middle Schools, the bid documents have
been prepared, and work has begun for the gymnasium air conditioning
projects. Work is scheduled to be
completed by July 31, 2006.
J. C. Booth Middle School documents
prepared for the renovations of the kitchen updates, as well as air
conditioning units in the gymnasium, have been approved by the Department of
Education. The modifications for the
renovation work (replacements of lockers, ceiling tiles, floor finishes, as
well as installation of the energy management system, interior painting and
installation of the marker boards) have also been approved the by the
Department of Education. The bid date
for these renovations is April 11, 2006, with the exception of the painting and
replacement of the floor finishes.
East Fayette Elementary School’s documentation for the
installation of an energy management system, replacement of the roof HVAC
units, and air conditioning of the gymnasium have been approved by the
Department of Education. The bid date
for this project is April 20, 2006.
For McIntosh
High School, the energy
management system, replacement of roof-top HVAC units, and the replacement of
ceiling tile and grid, installation of marker boards, modification to construct
a Health Occupations lab were submitted and approved by the Department of
Education. These items will be paid by
state money and FY 2001 Bond Funds, and will be bid out on April 25, 2006.
Brooks Elementary School has begun with the topographic
and boundary survey for the eight classroom additions. The architects and engineers are in process
of drawing up the paperwork necessary for the addition, air conditioning of the
kitchen, renovation of the media/auxiliary spaces, and the replacement of the
gymnasium roof and roof top HVAC units.
This project is expected to be completed in 2007.
The Fayette Middle School’s
projects are progressing, as well. The
architects and engineers are also in the process of drawing up the paperwork
necessary for adding air conditioning to the gymnasium, renovating the kitchen
and the replacement of the roof top HVAC units.
The project is expected to begin in August, 2006, and should be
completed in June, 2007.
Update on Inman
Elementary School: The school will be on a state-approved septic
system. Engineers and architects will be
drawing up the necessary paperwork for State approval, and the expected
construction begin date on the school will be in March, 2007. The excess 100 acres of the property have
been put up for sale, with a potential contract on the purchase, pending zoning
and Board approval, after an attempt to auction the property yielded no
bidders.
Mr. Lee Davis, Comptroller, informed the committee that the
second part of our bond issue would be floated at approximately July,
2007.
Dr. DeCotis informed the committee of the recently passed
new laws that will affect our school system.
For the class sizes law, he thinks we will not be affected, since we
already have smaller class sizes. We are
still plagued with austerity cuts, and the state will require us to hire
additional counselors in an attempt to prevent dropouts, and in addition, we
will need to hire additional teachers to keep up with the growth that Fayette County is experiencing. Another new law will require us to inform
parents about clubs that are offered for the children to participate in, and
give parents the option to “opt out” of
clubs, if they wish. Dr. DeCotis also
mentioned about the law allowing schools to teach the Bible as a class or
elective. The state sales tax proposal
this year did not pass, however we might see it again next year. In addition, the mandated PE law did not
pass, because the citizens put out a “grass-roots” effort in notifying the
legislators that they did not want the law to impede students from having art,
music or other fine arts classes offered.
Dr. DeCotis thanks the legislators for being very supportive this year.
The
meeting was adjourned. Dr. DeCotis
thanked everyone for coming and stated that he hoped they enjoyed the
meeting.