Minutes
Construction
Advisory Committee Meeting
September
25, 2006
Committee
members met at the Fayette County Board of Education Offices to discuss the ongoing
construction occurring within the school system. Mr. Lee Davis, Comptroller, welcomed the
members to the meeting, and members reintroduced themselves. As well, Mr. Davis introduced to the
Committee Mrs. Terri Gerhardt, who was recently promoted to Purchasing
Agent. Dr. John DeCotis, Superintendent,
and Mr. Davis thanked everyone for coming to the meeting.
Mr. Klaus Darnall, Construction
Manager, reported on most recent FY2005 bond construction projects. The additions to Spring Hill Elementary,
Peeples Elementary, and Rising
Starr Middle
Schools have been completed. Mr. Darnall also
stated that the J.
C. Booth
Middle School kitchen and
installation of new HVAC units in the gymnasium has almost been completed.
The construction on Bennett’s Mill Middle School
is still ahead of schedule. Rooftop HVAC
units and skylights have been installed.
The decking over the gymnasium is progressing; and the roof is 85%
complete. Exterior brick is also 85%
complete, and interior block work is moving ahead. Tile in the kitchen is beginning to be laid,
and heat pumps are being installed. The
capacity for this school will be just below 1,200 students. Weather permitting, the school will be on
schedule to be completed for August, 2007, however the contractor will try to
finish construction before this date.
At Fayette
Middle School, the
kitchen equipment and gymnasium HVAC units were bid on September 12, 2006. The kitchen renovations will begin within the
next couple of weeks, and a temporary wall will be installed to allow for the
demolition needed in the kitchen. The
food is being catered from the Lafayette
Educational Center
to the school, and the old band room is serving as the new serving line
area. The gymnasium HVAC units will be
installed next summer, and the replacement of the roof top units as well.
At Brooks Elementary School, the
space additions in the common areas; the HVAC units and new roof for the
gymnasium will be bid out on
October 3, 2006. It is expected that the Board of Education will
vote upon a recommended bidder at their October Board meeting.
Mr. Darnall
next spoke about renovations to occur at Oak Grove Elementary School’s kitchen. Updates to equipment, and a better pattern
for the serving area are being reviewed, and a schematic design is being drawn
up for approval to the State Department of Education.
The Fayette Board of Education’s
Internal Construction Committee is working on securing preliminary estimates
for the new elementary school. Even
though we receive State funds for middle schools and high schools, we will not
receive any funding from the State for this elementary school. When our newest elementary schools were
built, we paid approximately $68.00 per square foot, and now estimates we are
receiving are at $129.00 to $156.00 per square foot. Construction costs have increased due to the
demand for construction materials in China,
India,
and petroleum based material costs soaring because of recent gas
increases. As a cost-saving measure, the
Committee is looking at building a “prototype” school (such as Crabapple Lane
Elementary or Cleveland Elementary), where the architectural fees would be
reduced. Other options are also being
looked at, and will be discussed at a Called Board Meeting on October 30, 2006,
at 7:00 pm.
Mr. Mike Satterfield, Director of
Facilities Services, spoke about the projects that were part of the “10 year
plan” that were completed during the summer.
Almost all projects were completed, with the exception of the track at Sandy Creek High School, in which the asphalt is curing, and will
be paved and striped at the end of October, and the Fayette County
High School “Tiger
Stadium” lighting project. This will
involve the replacement of the stadium lights with new, updated lights.
Mr. Davis mentioned that the
second phase of bonds will most likely be sold during the summer of 2007. Of the $35 million in bonds, approximately
one-half of this amount has been drawn, and with the
completion of Bennett’s Mill
Middle School, bigger
draw downs are expected.
The
meeting was adjourned. Dr. DeCotis
thanked everyone for coming and stated that he hoped they enjoyed the meeting.